Rechercher dans ce blog

Thursday, August 26, 2021

Polymetal opts to fast track Prognoz silver mine due to high metal prices with processing at Nezhda concentrator - International Mining

Polymetal announces that its Board of Directors has approved an accelerated development of the open-pit mine at Prognoz with ore processing at the Nezhda concentrator. First payable concentrate production is expected in Q3 2023. “The decision to process ore from Prognoz at Nezhda ensures optimal allocation of human and financial capital within Polymetal. Fast-track development significantly reduces CAPEX requirements and project execution risks, while bringing cash flows forward and lowering environmental footprint,” said Vitaly Nesis, Group CEO of Polymetal.

Conventional open-pit mining will commence with pre-stripping in Q3 2022, with first ore mined in Q1 2023. The annual mine capacity will amount to 250,000 t of ore with average grade of approximately 600 g/t silver (Ag). Ore will be processed through the 2.2 Mt/y Nezhda concentrator. Recovery to high-grade clean silver-lead concentrate is expected to average 89%. Ore will be trucked by winter road from Prognoz to Nezhda production site (675 km) using contractors.

LOM payable Ag equivalent (AgEq) in concentrate is expected to comprise 120 Moz. Average annual payable AgEq production in 2023-2041 is estimated at roughly 6.5 Moz with an average AISC of $13.8/AgEq oz. The project’s upfront CAPEX to be incurred is estimated at $105 million comprising $20 million spending in 2021 for engineering and mine preparation and $85 million in 2022-2024, which includes investment in mining fleet, remote site infrastructure, roads, and pre-stripping. Project NPV and IRR stand at $154 million and 35% respectively at $20/oz silver price rising to $323 million and 60% at $25/oz price.

The rationale behind processing at Nezhda rather than building a processing plant onsite includes moving first payable production at least three years earlier enabling Polymetal to benefit from the favourable silver market. It also allows Polymetal to reduce project execution risks given remote location, harsh climate conditions, and likely acute deficit of personnel and contractors during the construction stage. It lowers initial CAPEX while maintaining attractive unit cash costs and thus driving higher returns and faster free cash flows. And it materially reduces environmental footprint: 20% lower GHG intensity due to grid connection at Nezhda, 50% lower fresh water intensity.

Adblock test (Why?)


Polymetal opts to fast track Prognoz silver mine due to high metal prices with processing at Nezhda concentrator - International Mining
Read More

No comments:

Post a Comment

Trump could push to eliminate restrictions to fast-track self-driving vehicles - Automotive News

[unable to retrieve full-text content] Trump could push to eliminate restrictions to fast-track self-driving vehicles    Automotive News T...